Building Inspections
Building Inspector -
Bob Bennett
Please call and make an
appointment to meet with the Building Inspector.
24-48 hours notice is required for all inspections. Occasionally the
building inspector can schedule an inspection the same day it is called for;
however, this is not always the case. After the inspection is completed, if
work is not marked “Approved” on the inspection form, make the corrections noted
in the remarks section of the form and call for another inspection before
continuing work.
It is fairly common for builders to order cement and then call for an
inspection. We DO NOT recommend this practice. Often the building
inspector is booked and can not make an inspection before the cement is due to
arrive. If this happens the builder will be expected to cancel his order for
cement. Pouring cement without an inspection will not be allowed. We recommend
waiting until the inspection has been completed and approved before ordering
cement.
Required Inspections &
Information
-
Inspect footing reinforcement before pouring
concrete footings. When this inspection is performed, the
property set-backs are checked to make sure all zoning property set-backs are correct.
-
Inspect the foundation wall reinforcement before
pouring concrete walls. We will inspect the foundation later for waterproofing coatings.
-
Any other
rebar.
-
Under
concrete floor inspection plumbing, electrical, mechanical).
-
Stitch and lag pier with
tie downs (manufactured homes only).
-
Inspect
rough framing and sheathing work. *
-
Inspect
rough plumbing work. *
-
Inspect
rough electrical work. *
-
Inspect
rough mechanical work. * (* The above 4 inspections can be done together, it's
called a 4-way inspection.)
-
Insulation.
-
Inspect power to panel &
trench.
-
Notify
the building inspector when starting laying of brick, installing of siding, or
applying other exterior finishes.
-
Notify the building inspector when starting to
apply roofing.
-
Notify
the building inspector when work starts on any fireplace or chimney if it is a
soul project.
-
Inspect rough drywall before taping and applying drywall mud.
-
Inspect
pressure test on gas line before back-filling
-
Other inspections: masonry, 4' masonry wall, or
bond beam.
-
Final
inspection.
The list of inspections above may not be
inclusive of all inspections required - contact the building official
if you have any questions concerning what needs inspection.
General Inspection
Rules:
-
Inspections must be called in 24 hours prior to
wanting inspection.
-
Concrete rebar inspections have priority over other inspections if called in 24 hr. prior to wanting
inspection.
-
DO NOT cover up anything requiring inspection -
Failure to do so will result in removal of covering, or complete condemnation of work.
-
All inspection tests are required. (Electrical,
plumbing, mechanical, etc.)
-
NO building can be occupied until final or a
temporary occupancy permit is issued by the Building Inspector.
-
All inspection cards and plans must be on the job
site during inspections.
-
A second re-inspection fee will be assessed against the
builder, contractor, or owner/agent.
-
A fee will be assessed to the
owner/agent (contractor) for not canceling a inspection in a timely manner if
they are not ready for the inspection.
|